K.07 · Supply Chain · 18 min read

Relocation from Asia. How a technically clean relocation runs in a structured way — including re-qualification, tool transfer and a double-running phase.

Relocations from Asia have been one of the most dominant topics in strategic purchasing since 2021. The reasons: lead-time risks, tariff increases, CBAM, ESG reporting, geopolitical stability. But implementation is demanding — technically, commercially and culturally. This article describes the playbook that we have developed across more than 40 relocations.

The four triggers — assessed realistically

Trigger 1: Lead time / volatility

Typical lead time from China to Europe (series delivery, sea freight): 10–14 weeks. That is sufficient in stable times. The problem: disruptions (pandemic, container shortages, customs backlogs) double the duration. Those who supply just-in-sequence lose out.

Trigger 2: Landed cost instead of unit price

The Chinese unit price was historically 35–50 percent below the European level. Today: tariff costs, freight, CBAM levies, warehousing costs for safety stock. On balance, the landed cost for many MIM parts is now only 5–15 percent below the EU level. For components with a weight < 10 g, the advantage is often nil.

Trigger 3: CO₂ and CBAM

The CO₂ footprint of a MIM part from China is typically 2.5 to 4 times higher than for EU production — mainly due to the energy mix (coal) and the transport distance. From 2026, CBAM accounts for this fully in financial terms.

Trigger 4: Quality and IP risks

On-site audits have been possible again in China since 2023, but with restrictions. Design protection, reverse-engineering risks and sub-supplier transparency remain critical.

First test question Does the relocation still pay off without taking CBAM into account? If yes, do it. If no, factor in the CBAM costs for 2026/2027 — then the calculation almost certainly tips.

The relocation playbook

Phase 1: Specification clarity (week 1–3)

Before anything can be relocated, the actual component specification must be reconstructed. Surprisingly often, the Asian series parts deviate from the official drawing — in the vast majority of cases without anyone having noticed. Our routine:

Phase 2: Tool decision (week 2–4)

Two routes: physically transfer the tool from China or build it new in Europe. The rule of thumb:

Phase 3: Dual-site qualification (week 4–12)

Our recommendation: design the relocation as dual sourcing from the outset. Two European plants are qualified in parallel — this increases the time required by 15–20 percent, but the strategic benefit is considerable.

Phase 4: Double-running (week 12–22)

Parallel supply from the old and new suppliers. Reduces the risk to zero, but temporarily doubles the warehousing costs. Typical sequence:

Phase 5: Phase-out of the Asian source (week 22–30)

Contract expiry, tool retrieval (if relevant), final PPAP for the new series state. Important: no premature cut — but a planned, controlled transition.

Critical risk points

Risk 1: Material availability. Asian suppliers frequently use feedstocks from local producers. In Europe these sometimes have to be re-sourced — delay risk 4–8 weeks.

Risk 2: Documentation gaps. Often no complete PPAP packages exist from the Asian production. As a result, reference values for the Cpk study in Europe are missing.

Risk 3: Unspoken specification drift. The Asian supplier has "optimised" the part over the years — usually to reduce its own costs. The differences often only become visible in the application.

Risk 4: Contractual legacy issues. Framework agreements with minimum quantities or tool-usage rights can delay the relocation or make it more expensive.

The role of the One-Supplier Model

In relocations, the classic bottleneck is the SRM onboarding of new suppliers. Each new addition means an audit, a framework agreement, an internal approval. In the One-Supplier Model this is completely eliminated: two new plants, but only one existing creditor number. Purchasing does not need to create new master data, and compliance does not need to carry out a new risk assessment.

Time savings For our customers, relocations take typically 22–30 weeks in the One-Supplier Model instead of 40–52 weeks in classic direct purchasing with two new suppliers. The savings arise almost entirely from the elimination of SRM onboarding.

Further reading

Questions about the topic of this article?

Our engineering and purchasing teams are available for technical enquiries — without obligation, without a form funnel.

Ask a question Knowledge Hub